Saturday, June 5, 2010

Date's and pics









Fascia/Gutter- 10/5/10
Roof Cover
-14/5/10
Elec roughing- 20/5/10 Lock up-4/6/10
Plaster-7/6/10

Thursday, May 13, 2010

Things are moving fast.




I am over the moon with all the progress Burbank's made. This week the roof has been done along with the builder's wrap and the bricks have now been delivered to start going up next week .

DATES
Slab 29/04/10
Frame 7/05/10
Gutters 10/05/10

Thursday, April 22, 2010

It's started



Earthworks 14/04/10
Set out 16/04/10
Drainage 21/04/10

Saturday, March 20, 2010

Some Changes and progress

Due to the developers not approving the first plans some changes were made. There is now a contrast brick which is La trobeand we also now require a panel lift garage door which will be Jasper.We also have some exciting news we now have a TAP.

Admin Dates

Deposit-30/10/09
Land-26/10/09
Colour selections- 1/12/09
Workings and drawings-15/01/10
Engineering-15/02/10
Developer Approval-15/02/10
Building Contract Signed-03/03/10
Building Permit-26/03/10

Sunday, January 17, 2010

The Final Plans





Plans are off to Developers for approval :-)

Monday, January 4, 2010