Almost but not quite






Our beautiful home is almost complete.
DATES
Painter-13/07/2010
Tiler-20/07/2010
Plumbing Fixtures-16/07/2010
Electrical Fit Off-26/07/2010
Plumbing Fit Off-23/07/2010
Carpet- complete but not ticked off

Still no word on PCI hopefully I have some new updates soon on this.

Thursday, July 1, 2010

More pics and dates







DATES

Fix out carpenter- 10/06/10
Fix Out- 20/06/10
Painting- in progress- should be completed next week sometime.

Saturday, June 5, 2010

Date's and pics









Fascia/Gutter- 10/5/10
Roof Cover
-14/5/10
Elec roughing- 20/5/10 Lock up-4/6/10
Plaster-7/6/10

Thursday, May 13, 2010

Things are moving fast.




I am over the moon with all the progress Burbank's made. This week the roof has been done along with the builder's wrap and the bricks have now been delivered to start going up next week .

DATES
Slab 29/04/10
Frame 7/05/10
Gutters 10/05/10

Thursday, April 22, 2010

It's started



Earthworks 14/04/10
Set out 16/04/10
Drainage 21/04/10

Saturday, March 20, 2010

Some Changes and progress

Due to the developers not approving the first plans some changes were made. There is now a contrast brick which is La trobeand we also now require a panel lift garage door which will be Jasper.We also have some exciting news we now have a TAP.