Some Changes and progress
Due to the developers not approving the first plans some changes were made. There is now a contrast brick which is La trobe
and we also now require a panel lift garage door which will be Jasper.
We also have some exciting news we now have a TAP.
Admin Dates
Deposit-30/10/09
Land-26/10/09
Colour selections- 1/12/09
Workings and drawings-15/01/10
Engineering-15/02/10
Developer Approval-15/02/10
Building Contract Signed-03/03/10
Building Permit-26/03/10
Newer Posts
Older Posts
Home
Subscribe to:
Posts (Atom)
Our Burbank Ascent 2500
Blog Archive
▼
2010
(10)
►
August
(2)
►
July
(1)
►
June
(1)
►
May
(1)
►
April
(1)
▼
March
(2)
Some Changes and progress
Admin Dates
►
January
(2)
►
2009
(7)
►
December
(4)
►
November
(3)
Followers
Subscribe To
Posts
Atom
Posts
All Comments
Atom
All Comments
Botanic Ridge
http://botanicridge.com.au/
Burbank Ascent
http://www.burbank.com.au/HouseDetails.aspx?houseId=81